How does Project Management Costs vary with the size of the whole (software development) project?

If you consider that the project management is a percentage of the total project cost, it appears to me that this percentage varies with the size of the project (not considering the hidden costs). Consider the case of software development project. How would that curve (cost of management versus total cost) appear like?

In my experience as a software development project manager for a consulting / developing firm we added 25% – 35% of project management cost ON TOP of the actual development cost.

The reasoning for this is that the PM is the link between the customer of the project and the developers. Often they speak two different languages and you need the PM in between in order to “translate”.

The range of 25% – 35% depended on the customer. If we knew that the customer was “easy” to deal with, then we could usually get away with only adding 25%. But if the customer required more hand holding and was generally “difficult” then we went as high as 35% because the PM would need to invest a lot more time into the project.

Until next time,
Cornelius Fichtner, PMP
The Project Management PrepCast™ – http://www.pm-prepcast.com
The Project Management Podcast™ – http://www.thepmpodcast.com

powered by yahoo answers

Software Project Survival Guide (Pro -- Best Practices) Software Project Survival Guide (Pro -- Best Practices)
$10.00

The author of the classics "Code Complete" and "Rapid Development" throws a lifeline to the industry's huge and indispensable population of rookie managers and technical leads. This book is a roadmap to how an effective software project works--understandable even for those with limited project experience....
UNIXWARE MEDIA KIT V2.1.3 UNIXWARE MEDIA KIT V2.1.3

...
The Mythical Man-Month: Essays on Software Engineering, Anniversary Edition (2nd Edition) The Mythical Man-Month: Essays on Software Engineering, Anniversary Edition (2nd Edition)
$23.80

The classic book on the human elements of software engineering. Software tools and development environments may have changed in the 21 years since the first edition of this book, but the peculiarly nonlinear economies of scale in collaborative work and the nature of individuals and groups has not changed an epsilon. If you write code or depend upon those who do, get this book as soon as pos...
Agile Project Management with Scrum (Microsoft Professional) Agile Project Management with Scrum (Microsoft Professional)
$23.98

Apply the principles of Scrum, one of the most popular agile programming methods, to software project management—and focus your team on delivering real business value. Author Ken Schwaber, a leader in the agile process movement and a co-creator of Scrum, brings his vast expertise to helping you guide the product and software development process more effectively and efficiently. Help eliminate the...
Kanban Kanban
$32.36

...